Erco Oil Refinery
United Arab Emirates
 
 
Location
Sharjah, UAE
Client
Unity Contracting LLC
Construction Cost
Dh 15.0 million

 

 General Cargo Wharf

  

General Cargo Wharf

   The structure is founded on bored piles tied together utilising reinforced concrete ground slab and beams.

Erco Oil Refinery

Steel-framed nine-level refinery building of 4,500 square metres floor area. The documentation was prepared in consultation with the contractor for a "design and construct" contract. The contract had a very short construction period, and all documentation was completed on schedule within 21 days, including close liaison with the refinery equipment manufacturer in Belgium.

 